Project Number
|
Project Title
|
Construction Schedule
|
Remarks
|
|
PK.07.604.HE/GF.004 |
Institute of Health Science Dallas |
9/08-12/11 |
Minor changes in progress. |
|
DE.07.009.TRB.005 |
Science Building Renovation & Expansion |
9/08-8/11 |
New Addition complete, Renovation in progress. |
|
DE.05.037.TR.061 |
Stoddard Hall Exterior Improvements |
12/10-08/11 |
In Construction |
|
DE.07.102.NP.067 |
Fitness and Recreation Center |
1/10-7/11 |
Construction in progress. |
|
DE.03.999.TR.054 |
Infrastructure Upgrades (Electrical) |
7/10-1/12 |
Work in Progress |
|
DE.09.015.PA.008 |
MCL Food & Beverage Service Kiosk |
TBD |
2011 Summer Project |
|
DE.09.037.BT.001 |
Professional Education Renovation |
||
|
DE.09.012.BT.005 |
Old Main Laboratory Space Renovation |
|
|
|
PK.07.604.HE/GF.004 |
Institute of Health Science Dallas Center Parking Garage |
Work in Progress |
|
|
DE.10.042.PA.004 |
Create Storage Room Stark Hall |
|
|
|
DE.10.044.PA.013 |
Stark/Guinn Commons Roof Replacement |
Design Complete. Need Funds for Abatement |
|
|
DE.10.042/043.PA.007 |
Electrical Infrastructure Improvement (Interior for Stark/Guinn) |
7/10-5/11 |
Design complete, Work in Progress |
|
DE.10.000.MRR.020 |
Parking Lot at former Reagen Houston site. |
3/11-6/11 |
In Construction. |
|
DE.11.042/043.PA.002 |
Stark/Guinn Room Renovations |
Ongoing |
|
|
DE.05.999.TR.60 |
Infrastructure, Drainage and sidewalks. |
12/10-1/11 |
Study complete. Drainage 55% complete. |